| Widely experienced (30 years +) in Oil & Gas exploration |
|
Resume built for oil and gas job opportunities by a jobseeker with experience in Widely experienced (30 years +) in Oil & Gas exploration - would you like to offer this candidate a job/contract employment? Please contact us OR search for another relevant oil CV/Resume in our impressive oil industry database
CV/Resume ID no.:
75025
Last Updated:
Monday, June 25, 2007 |
Location (Residence): Kuwait, Kuwait
Citizenship: Egypt
|
| |
Languages:
Native:
Arabic Egypt Other:
English |
| |
| Education & Experience: |
Work Authorization & Relocation: |
|
|
Education:
Bachelors in Electrical Power Years of Experience:
30 years
|
Authorized to work in:
Algeria, Bahrain, Jordan, Kuwait, Libyan Arab Jama., Oman, Qatar, Saudi Arabia, Sudan, Syrian Arab Rep., United Arab Emirates
Present Location:
Kuwait, Kuwait
Relocation:
Egypt, Jordan, Kuwait, Libyan Arab Jama., Oman, Qatar, Saudi Arabia, Sudan, Syrian Arab Rep., United Arab Emirates |
|
| |
| Expertise |
| Category |
Subcategory |
Ability |
Experience |
|
Plant (Refinery, Gas...) |
Refinery Plant |
Experienced
|
20 years |
|
Plant (Refinery, Gas...) |
Refinery Plant |
Experienced
|
5 years |
|
Engineering |
Electromechanical |
Expert
|
12 years |
|
| |
| CV/Resume Details |
| |
| 1. Summary (Cover Letter) - CV/Resume Part 1 [Mandatory] |
Dear Sir.
I have 25+ years experience in Oil & Gas refineries in Electrical Engineering field, 17 years of which working by KNPC “Kuwait National Petroleum Co.”.
Now I am working for NRP, Kuwait “New Refinery Project” with capacity 600 000 BPCD, PMC by Fluor, US.
Thanks.
|
| 2. Work Experience - CV/Resume Part 2 [Mandatory] |
Education : B.Sc. Electric Power (with V.Good)
Training Courses :
Fire Alarm/Extinguishing system (Pyrotechnics)
Basic element of digital devices (ISA)
Inspection & Maintenance of Elec. Equipment in hazard areas.
Grounding and shielding.
Power system operation and control by using PC.
Experiences:
Feb., 2005 till date: Working by KNPC, NRP “ New Refinery Project” , Kuwait, 600 000 BPCD PMC by Fluor , US.
July, 00 till Feb. 2005 : Employed by Egyptian Petroleum Maintenance Co.(EMC) working as Electrical Consultant Engineer (part time).
Job Description :Providing studies for develop and up-grading the electrical net-work system, gas- turbine control system. Design and install new fire extinguish system for client “General Petroleum Co. GPC.
Employed by National Consulting Bureau- Kuwait as trainer/ on site instructor.
Job Description : Preparing training programs, elect. courses to improvement elect. engineers, UD skils.The following courses are conducted (as example).
Electrical equipment in hazardous area at Qatar Liquefied Gas Co. (two courses).
Electrical equipment in hazardous area at Abu Dhabi Liquefied Gas Co. ADGAS (Das
Island).
Electrical Equipment installation in petrochemical plant At National Petroleum
Co. (KNPC) Kuwait.
March, 1985 to July, 00 (15 years): Employed by Kuwait National Petroleum Co. KNPC as bellow
From May, 1994) to July, 00 : I was working as Electric Design Engineer (Projects Department).
Job Description : Preparing specification, drawings, standards, tender document, materials procurement, evaluation the Bidders’ document/offers, materials inspection, factory acceptance tests, site acceptance tests, etc.. for EPC Contracts
(Engineering, Procurement & Construction Contract), EC Contracts (Engineering, &
Construction Contract) or Construction Contract as below:
Sea Water Return Line Modification Project (Construction Contract) at total cost
KD/500,000. The electrical part consists of install two new 3.3 KV pumps with
associated control valves, civil works, cable works, piping, electrical 3.3
KV/440V switch gears, PLC, etc…
My activity was design, procurement all materials 3.3 KV motor starters (
Toshiba), 440V motor starters (Tojami), 3.3KV/440V power cables, control cables,
ground system, etc.. preparing tender document for construction work.
AGRP (EPC Contract) at total cost KD/125 million, electric part of the project
consists of three nos. of new package type substations each has two nos. of 8
MVA power transformers 11/3.3KV, Two nos. of 1500 KVA, 3.3/0.4 KV transformers,
3.3/0.4 switch gears, MCC (Motor Control Center), fire alarm system, emergency
diesel generator, cabling system, etc..
My activity was preparing EPC tender document, evaluation the bidders, review
and make comments on the successful contractor engineering works and materials
offered by contractor.
MAFP, at total cost KD/85 million, EPC contract, electric part of the project
consists of one no. of new package substation Fuji type, has two nos. of 10 MVA
power transformers 11/3.3KV, Two nos. of 1500 KVA, 3.3/0.4 KV transformers,
3.3/0.4 switch gears, MCC (Motor Control Center), fire alarm system, emergency
diesel generator, cabling system, etc..
My activity was preparing EPC tender document, evaluation the bidders, review
and make comments on the successful contractor engineering works and materials
offered by contractor.
North Pier Loading Arms Project at total cost KD/1.25 million, Construction
contract, electric part of the project consists of provide power supply /earth
system to the 12 nos. of loading arms with associated power and control cables,
440V switch gears (all materials are suitable for hazard area).
My activity was preparing tender document for electrical part of construction
works, procurement power/control cables, conduit materials, classified 440 V
switch gears, evaluation the bidders, review and make comments on the successful
contractor engineering works.
FOSP(Fuel Oil Supply Project) at total cost KD/6.5 million, EPC contract,
electric part of the project consists of Provide new package substation, 11 KV
switch gears, 0.440 V switch gears/ MCC, 1500 KVA transformers, 11/0.4 KV,
diesel generator for emergency power supply, UPS 40 KVA 110V AC, 110 VDC
battery charger, fire alarm system, power supply to three nos. of 1200 HP
pumps, lighting system for hazard area.
My activity was preparing EPC tender document, evaluation the bidders, review and
make comments on the successful contractor engineering works and materials
offered by contractor.
New Off –Gas Compressor And Modification on the two existing compressors at
total cost KD/500,000, construction contract, electric part of the project consists
of provide power supply /earth system to the new compressor 1200 HP 3.3 KV, with associated new power supply to the lube oil pump/heater, extend the existing compressors shelter with associated lighting system.
My activity was preparing tender document for electrical part of construction
works, procurement 3.3/0.4 KV power/control cables, conduit materials, 3.3 KV
switch gear Toshiba type, 440 V power unit for oil heater, 440V starter Tojami
for lube oil pump, evaluation the bidders, review and make comments on the
successful contractor engineering works.
Restoration works for old CDU #3 unit at total cost KD/4 million, construction
contract, electric part of the project consists of provide power supply /earth
system to the new 28 nos. of new pumps and compressors, with associated
power/control cables, new 3.3/0.4 KV switch gears, fire alarm system, battery
charger, up-grading of the existing lighting system, new ground system, provide
interlock/signal status to control room.
My activity was preparing of electrical part of tender document, procurement
3.3/0.4 KV power/control cables, conduit materials, EXD lighting fittings, EXD
lighting panels.
March, 1985 to May, 1994 : I working as Area Electrical Maintenance Engineer.
Job Description: Commissioned, start-up and maintain the new elect. System for the new RMP refinery (Refinery Modernization Project) In Mina Al-Ahmadi Refinery, at total cost KD/580 million. RMP was built by JGC Company (Japan).
RMP electric system consists of.
* Main bulk substation (11KV, 180 MVA, Mitsubishi manufactured), consists of
11KV vacuum circuit breakers (6nos. for incomer feeders, 4nos for IS limiters,
4 nos. for bus ties, 4 nos. for 11 KV compressors motor feeders, 38 nos. for
substation feeders), battery charger remote control panels .
* Package type substations 15 Nos. Fuji manufactured (Japan), each substation
consists of 11KV incoming feeder 2 nos., 11/3.3KV, 8MVA transformers Brush
type, 4nos. 3.3/0.440 KV, 1250 KVA transformers, 3.3 KV Vacuum circuit breakers
Toshiba type, 440V Air circuit breakers, MCC(motor control center) Tojami type,
fire alarm system (Pyrotechnics) and battery chargers.
* UPS system 14 nos. 60 KVA, 110 V AC, Gutor manufactured.
* High capacity of 11KV/3.3KV motors and 440 V motors (for classified areas).
* Lighting system ( for hazardous areas) .
* Emergency power system (diesel generators) 3.3KV and 440V.
* 11KV, 3.3KV and 440V power cable system, control cables, grounding/lightining
system and conduit system.
December, 1978 to March, 1985 : Employed by Abu-Qir fertilizer and chemical industries in Alex. Egypt, as chief of the section of elect. maintenance department.
Job Description : Construction, commissioning, start-up and maintain of one line of Ammonia/Urea Plant, 1500 T/D Urea.
Elect. work consists of : Main substation, 66 KV, BBC (ABB) manufactured.66/6.6 KV receiving substations two nos., AEG manufactured (German), complete
with power transformers 6.6/0.38 KV 6nos., 6.6KV minimum oil circuit breaker for
6.6KV motors, bus-ties, incomers, battery charger, UPS (Seimens), interlock system (Logic).
12.5 MVA steam generator, 6.6 KV associated with control panel, protection system.
6.6/0.38 KV motors, lighting system.
Emergency power supply (diesel generator).
January, 1977 to December, 1978 : Employed by Misr Rayon Co. Egypt. As maintenance engineer.
Job Description : Construction, commissioning, start-up and maintain of Steam Power Station consists of three units each 12 MVA, AEG type with associated controls, protection system, switch gears, power cables.
May, 1970 to January , 1977 : Employed by Organization Of Roads and Bridges, Alex. Egypt., as maintenance Engineer.
Job Description : Responsible for workshops, maintain elect. Motors, agitator/crusher machines, motor rewinding, etc.
|
| 3. Education & Training - CV/Resume Part 3 [Mandatory] |
BSc
|
| 4. Computer Skills - CV/Resume Part 4 [Mandatory] |
Microsoft
|
| 5. Other Skills - CV/Resume Part 5 [Optional] |
Nothing
|
| 6. Additional Information - CV/Resume Part 6 [Optional] |
Nothing
|
| |
|