CV SACS Offshore Structural Design Engineer, STAAD, SACS, AUTOCAD
|
|
|
|
|
|
|
| |
| |
| SACS Offshore Structural Design Engineer, STAAD, SACS, AUTOCAD |
|
Resume built for oil and gas job opportunities by a jobseeker with experience in SACS Offshore Structural Design Engineer, STAAD, SACS, AUTOCAD - would you like to offer this candidate a job/contract employment? Please contact us OR search for another relevant oil CV/Resume in our impressive oil industry database
CV/Resume ID no.:
82935
Last Updated:
Tuesday, August 26, 2008 |
Location (Residence): Hulu Klang, Malaysia
Citizenship: Malaysia
|
| |
Languages:
Native:
Malay Malaysia Other:
English |
| |
| Education & Experience: |
Work Authorization & Relocation: |
|
|
Education:
Bachelors in Civil engineering Years of Experience:
8 years
|
Authorized to work in:
Malaysia
Present Location:
Malaysia, Kuala Lumpur
Relocation:
European Union, UK (in particular), Australia, Brunei Darussalam, Denmark, Finland, France, Italy, Malaysia, Monaco, Netherlands, New Zealand, Norway, Saudi Arabia, Singapore, Sweden, United Kingdom |
|
| |
| Expertise |
| Category |
Subcategory |
Ability |
Experience |
|
Engineering |
Structural |
Experienced
|
13 years |
|
Design/Software |
Structural |
Experienced
|
13 years |
|
Design/Software |
STAAD |
Experienced
|
13 years |
|
Engineering |
STAAD |
Experienced
|
13 years |
|
| |
| CV/Resume Details |
| |
| 1. Summary (Cover Letter) - CV/Resume Part 1 [Mandatory] |
Dear Sir,
I would like to apply a suitable position in your company based on my 8 years experience in structural engineering. I had 5 year experience in construction, 2 year in design and a year with Oil Company.
I appreciate your kind consideration for any suitable position.
|
| 2. Work Experience - CV/Resume Part 2 [Mandatory] |
DETAILED OF WORKING EXPERIENCES
Murphy Sarawak Oil Co. Ltd
Offshore Marginal Development Project (Engineering)
STRUCTURAL ENGINEER
May ’07 – Present
Gas Dev. Project Murphy Sarawak Oil Co. Ltd Eng. Department
(May ’07 – present)
• Design and project management for detail design, engineering, fabrication and installation of 5 platform for Sarawak Gas Development Project
• MTO checking and preparation for purchasing structural steel
• Prepared structural steel ITB for procurement
• Supports offshore installation team such as gangway design, conductor access frame, crane supporting structure, padeye check, rigging, piling, fairlead support, winch base support, air tugger base support etc.
• Reviewed the fabricator foundation study, upending procedure, loadout procedure etc.
• Review the offshore installation contractor document and report such as strengthening analysis & calculation for SERF, Mechanical layout for SERF, Helideck redesign report, jib crane, crane reinforcement, seafastening, mooring, motion study etc.
• Support installation and offshore construction team during installation campaign.
• Review and check design document, report and drawings from design consultant.
• Coordination meeting with installation contractor.
• Participate for Technical Bid Evaluation(TBE) for Topside Steel/piles and pre award meeting
• Pre production meeting for supplied SAW tubular at Sam Kang Industries, Korea.
• Prepared installation procedure such as SERF preparatory, Design Basis, Marine Operation, Loadout, etc.
• Participate in PreSPUD meeting for preparation to offshore installation
• Involved in answering STQ from fabricator
• Site visit and verification for jacket fabrication & SERF fabrication
• Assist the installation lead for managing and planning offshore installation activities and field engineer offshore
• Liaise with IVP for all structural design document from consultant
• Coordinate with MWS for all marine operation including loadout, transportation, mooring, lifting, piling and grouting
Rnz Integrated (M) Sdn Bhd
Civil/Structural Department
CIVIL/STRUCTURAL DESIGN ENGINEER
June ’05 – May’07
MLTTB PETRONAS CARIGALI SDN BHD RNZ INTEGRATED
(Sept ’06 – May’07)
• Conceptual for MLTTB at Mustang Melbourne office
• Fabrication yard & barge survey report
• Penang Workshop for MLTTB conceptual presentation
• Resak structural integrity reanalysis and report
• FEED design for Modules 1,2,4 & 5 includes inplace, loadout, lifting and transportation analysis.
BE Integrated Deck MEARSK OIL QATAR(BID) RNZ INTEGRATED
(Aug ’06 – Sept ’06)
• Inplace, transportation, installation and lifting analysis for BG Topside for FEED(Bid)
• Prepare WCR(Bid)
BNDP-J WPU Workover PETRONAS CARIGALI SDN BHD RNZ INTEGRATED
(Aug ’06 – Sept ’06)
• Inplace reanalysis and report
• Workover drawing packages
• Scope of work & specification
BO-D Jacket TALISMAN MALAYSIA LIMITED RNZ INTEGRATED
(June ’06 – Jul ’06)
• Detailed design of BOD jacket
• Prepare Lifting, loadout, on-bottom and transportation analysis
• Generate lifting weight
• Lifting trunion design
Sumandak Integrated PH II(Supg-B & Sujt-C) PETRONAS CARIGALI S/B RNZ INTEGRATED
(Sept’05 – Dec’05)
• FEED for Sumandak Integrated Phase II – Modular platform concept
• Involved in on-bottom analysis, stability and report’s for Sujt-c substructure
• Designing of mudmat framing and checked the drawing for Sujt-c
• Designing the Module 3 for Supg-B Topside(Modular concept)
• Prepare analysis and report for module 3 inplace, loadout, lifting and transportation as well as blast analysis
• Review and check all drawing for module 3
BT-A Monopod Project TALISMAN MALAYSIA LIMITED RNZ INTEGRATED
(June ’05 – Sept’05)
• Involved in on-bottom analysis, stability and report’s
• Designing of mudmat framing and checked the drawing
PETRONAS CARIGALI SDN BHD RNZ INTEGRATED
(June ’05 – Aug’06)
• Water Capacity Improvement at MCOT – water tank extension
• BDP-G gin pole design
• TKQ-A inplace reanalysis for replacement of Air Compressor
• BOK-A reassessment report for replacement of Air Compressor
• WLDP-C WPU workover package, including reanalysis, drawing, lifting
• WLDP-A Platform – model validation, inplace & softmooring analysis.
Saipem Pte Ltd( Singapore) @SMOE site office
Construction Engineering Department
CONSTRUCTION/STRUCTURAL ENGINEER
Aug ’04 – May’05
ERHA FPSO EPC1 Project ESSO Exploration & Production Nigiria Ltd SAIPEM
(Aug ’04 – May’05)
• Involved in construction engineering(Methodology) activities as construction engineering engineer for construction work specially for construction methodology such as lifting, skidding, loadout, weighing, transportation, clash review, installation aids, ballasting, dredging, riggings, floating vessel, FPSO hull etc.
• Reviewed and checked all documentation related to the activities such as loadout procedure, lifting procedure, FPSO crane, bearing pad procedure, etc.
• Coordinate between contractors(HHI/MSE/SMOE/Vendor), client, sub contractor for interface solution for the construction methodology i.e. heavy lifting, skidding, loadout, weighing, equipment installation etc.
• Review and check all procedure for Loadout, lifting, weighing, skidding, etc from contractor(SMOE/MSE).
• Monitor and check the WCR and compare with actual report from weighing.
• Review and check the mooring & ballasting analysis and calculation for FPSO, crane barge and transportation barge.
• Weekly meeting for the construction method with contractor and client.
• Review and check the hydrographic survey report.
• Involved in all interface for the integration of modules on the Hull (FPSO).
• Check and review the installation guide design, bumper and stopper guide.
• 13 heavy lift modules in 13 days with total weight 10,000MT lifted on the FPSO for integration of 1st lift campaign.
• 13 heavy lift for 2nd lift campaign with total weight 18,000MT.
• Reviewed and check the bearing pad procedure and installation.
• Conducted the debriefing session for look ahead schedule and lesson learned for next lifting.
• Coordinate with vendor and construction for all equipment for installation and integration.
• Participate in Risk Assessment Session for all integration of topside on to FPSO.
• Involved in Lesson Learned Session for 1st lift campaign.
• Monitor surveyor for the coordinate survey preparation especially for clash check.
• Involved in Site Instruction for additional work to be done by sub contractor. Monitor work perform and review the time sheet for the work perform.
SIME SEMBCORP. ENG. SDN. BHD.
Engineering Department (Structural Department)
STRUCTURAL ENGINEER(Lead)
Jan ’04 – July ‘04
GU-E Topside(MSF,6 Modules, Bridges) EXXONMOBIL MALAYSIA(EMEPMI) SSE
(Jan ‘04 – July ‘04)
• Involved in engineering activities such as foundation study, weighing analysis, lifting analysis, lifting procedure, erection sequence, preliminary loadout procedure, meetings, shopdrawing, MTO, WCR, TBE, RQ and STQ.
• Reviewed and checked all document issued to client.
• Involved in weekly engineering-procurement interface meeting with client.
• Coordinate between inter department, vendor and client through out the project for Structural Issues.
• Prepare and checking all engineering works, lifting and loadout procedure as well as Engineering procedure.
• Design drawing and fabrication drawing checked.
• Involved in weekly internal meeting, client meeting and interface loadout meeting with Offshore Installation Contractor.
Ÿ Review and comment for planning package for all modules.
Ÿ Involved and coordinate for interface clash check with other disciplines by using PDMS. Discussed and resolved the clash with Client.
SIME SEMBCORP. ENG. SDN. BHD.
Engineering Department (Structural Department)
STRUCTURAL ENGINEER / ENG. COOR. /HEAD OF DEPARTMENT (SSE branch Teluk Ramunia)
July ’02 – Dec ‘03
GU-F & IB-C Tripod Jacket EXXONMOBIL MALAYSIA(EMEPMI) SSE
(June ’03 – Dec ’03)
• Involved in engineering activities as structural lead for fabrication such as foundation study, roll-up analysis, weighing analysis, lifting analysis, lifting procedure, preliminary loadout procedure, meetings, shopdrawing, MTO, TBE, RQ and STQ.
• Monitored and managed all structural department activities at Teluk Ramunia branch yard for all operation requirements.
• Reviewed and approved all document issued to client.
• Managed and planned for department for day-to-day activities as well as department future planned.
Bongkot SMOE(S’pore) SSE
(June ’03 – Dec ‘03) Ultimate Client - PTTEP, Total Fina Elf(Thai.)
• Involved in engineering activities as structural lead for fabrication such as foundation study, roll-up analysis, weighing analysis, lifting analysis, lifting procedure, preliminary loadout procedure, meetings, shopdrawing, MTO, TBE, RQ and STQ.
• Monitored and managed all structural department activities at Teluk Ramunia branch yard for all operation requirements.
• Reviewed and approved all document issued to client.
• Managed and planned for department for day-to-day activities as well as department future planned.
Amenam AMP2 jacket SAIBOS(France) SSE
(Dec ‘02 – Dec ‘03) Ultimate client – Total Fina Elf & NNPC(Nigeria)
• Involved in engineering activities as structural lead for fabrication such as foundation study, roll-up analysis, weighing analysis, lifting analysis, lifting procedure, preliminary loadout procedure, meetings, shopdrawing, MTO, WCR, TBE, RQ and STQ.
• Monitored and managed all structural department activities at Teluk Ramunia branch yard for all operation requirements.
• Reviewed and approved all document issued to client.
• Managed and planned for department for day-to-day activities as well as department future planned.
KTMP-A Jacket/Topside SARAWAK SHELL BERHAD(SSB) SSE
Ketam Decommissioning
KTV-A Tripod(Aug’ 03 – Nov ’03)
• Involved in engineering activities as structural lead for decommissioning work start form arrival of the barge until cutting work for the structure. Main activities are load-in procedure and cutting(reverse erection) procedure.
• Monitored and managed all structural department activities at Teluk Ramunia branch yard for all operation requirements.
• Reviewed and approved all document issued to client.
• Managed and planned for department for day-to-day activities as well as department future planned.
YP, ZBA & YB Jacket/ Topside YOHO EPC2 PROJECT – Saipem-SA(France) SSE
(Oct ‘02 – Nov ‘03) Ultimate Client – ExxonMobil(Houston) & NNPC(Nigeria)
• Involved in engineering activities as structural lead for fabrication such as foundation study, dredging, ballasting, skidding procedure, roll-up procedure, lifting analysis, lifting procedure, weekly meeting, shopdrawing, MTO, WCR, RQ, TBE, STQ, Shiploose list and Loadout for YB, ZBA and YP jacket.
• Monitored and managed all structural department activities at Teluk Ramunia branch yard for all operation requirements.
• Reviewed and approved all document issued to client.
• Managed and planned for department for day-to-day activities as well as department future planned.
• Company Representative at Client office SAIPEM(SEI) London for 2 month to coordinate all engineering issues as well as expedited and resolved all engineering deliverables for 2 Topside and 3 Jacket.
B11P-A Jacket SARAWAK SHELL BERHAD(SSB) SSE (June ‘02 – Dec ‘03)
• Involved in engineering activities as structural lead for fabrication such as lifting analysis, lifting procedure, shopdrawing, MTO, WCR, RQ, STQ, Shiploose list and Loadout.
• Monitored and managed all structural department activities at Teluk Ramunia branch yard for all operation requirements.
• Reviewed and approved all document issued to client.
• Managed and planned for department for day-to-day activities as well as department future planned.
General Duties & Responsibilities
• Coordinate between inter department, vendor and client throught the project
• Checking all engineering output such as lifting and loadout procedure, Engineering procedure, shopdrawing, MTO, TBE, WCR, RFQ and STQ.
• Involved in weekly internal meeting, client meeting and interface meeting with Installation contractor.
Ÿ Review and comment for planning package for all projects.
SIME SEMBCORP. ENG. SDN. BHD.
Engineering Department(Structural Department)
STRUCTURAL ENGINEER/ENG. COORDINATOOR
June ’00 –June ‘02
M1 Expansion Package A & B SARAWAK SHELL BERHAD(SSB) SSE Dec ‘01 –July ‘02)
• Involved in engineering activities as structural engineer as well as engineering coordinator for fabrication such as lifting analysis, lifting procedure, MTO, WCR, RQ, STQ, Shiploose list and Loadout for platform expansion project.
• Participate in Constructability Review at Technip KL office with OIC, Consultant, Client, Subcontractor etc for ease of installation work offshore.
E11R-B Modification & Tie-In SARAWAK SHELL BERHAD(SSB) SSE
(Oct ‘01 – April ‘02)
• Involved in engineering activities as structural engineer for fabrication such as lifting analysis, lifting procedure, MTO, WCR, RQ, STQ, Shiploose list and Loadout for offshore platform expansion project.
• Offshore visit at E11R-B Platform offshore Miri, Sarawak for 5 days to verify the extension work to be carried out.
Bintang A & B Jacket & Topside ESSO PRODUCTION MALAYSIA, Inc.(EPMI) SSE (August ‘01 –May ‘02)
• Involved in engineering activities as structural engineer for fabrication such as lifting analysis, lifting procedure, MTO, WCR, RQ, STQ and TBE.
ANPG-A Topside and Jacket PETRONAS CARIGALI SDN. BHD. BHD.(PCSB). SSE
(June ‘00 - Feb ‘02)
• Involved in engineering activities as structural engineer for fabrication such as lifting analysis, lifting procedure, MTO, WCR, RQ, STQ, TBE, Hydrographic Survey and Loadout.
General Duties & Responsibilities
Ÿ Offshore visit for E11RB Modification work at Miri offshore. Taking picture, measurement, feasibility, installation method study etc.
• Coordinate between inter department, vendor and client throught the project
• Perform all engineering calculation for foundation, fabrication, temporary suport, lifting and loadout procedure as well as other engineering procedure.
Ÿ Involve in prepare the load out procedure for skidding, lifting and boogey including ballasting calculation.
Ÿ Responsible for preparing ship loose list for structural item and compiling for all the ship loose list from other disciplines.
Ÿ Perform structural analysis using SACS(Structural Analysis Computer Software) for lifting procedure, foundation study and local check analysis.
• Prepare all engineering output such as lifting and loadout procedure, Engineering procedure, shopdrawing, MTO, TBE, WCR, RFQ and STQ.
• Involved in weekly internal meeting, client meeting and interface meeting with Installation contractor.
Ÿ Review and comment for planning package for all projects.
|
| 3. Education & Training - CV/Resume Part 3 [Mandatory] |
Ÿ SACS Analysis
Ÿ STAAD Pro
Ÿ TBC Team Builders
Ÿ Offshore Safety Induction &
Ÿ Basic Firefighting and Self-resque
Ÿ H2S Awareness Course
Ÿ Negotiation Skills
Ÿ Finance for Non-finance Exec.
Ÿ Bussiness Writting Skills
Ÿ Occupational, Safety and Health
Ÿ Safety Oriention Course
Ÿ Supervisory Skills
Ÿ Presentation Skills
Ÿ The Practicle Art & Science of Planning,
Organising & Information Management
Ÿ Creative Problem Solving & Decision
Making
Permit to work trainning
(22/10/2004)
Ÿ Confine Space Training
|
| 4. Computer Skills - CV/Resume Part 4 [Mandatory] |
SACS – Structural Analysis Computer Sys. Ver. 5.2 sp2
StaadPro 2002(Basic)
AUTOCAD 2006
MS Office – Word, Excel, Power point
Lotus – 123 & Word Pro
|
| 5. Other Skills - CV/Resume Part 5 [Optional] |
NIL
|
| 6. Additional Information - CV/Resume Part 6 [Optional] |
-
|
| |
|
|
|
|
|
SACS Offshore Structural Design Engineer, STAAD, SACS, AUTOCAD
CV/Resume ID no.: 82935 |
|
|
|
|
|
|
| Relevant CVs; view more oil and gas CVs |
| 1. Structural PDMS Designer (17) |
| 2. Piping Designer working with Compelmada International, s.a. Portugal |
| 3. Structural Designer |
| 4. Structural Engineer, SAP 2000, Space Gass |
| 5. PDMS & PDS Designer - Structural |
| 6. Civil geotechnical engineer, young I aim to be involved in new challenging projects. |
| 7. Team Leader, X-steel Structural , Having 9 + years of experience |
| 8. PDS Lead Designer (Civil & Structural) |
| 9. Lead Structural PDMS Designer |
| 10. Designing, Planning, Estimation |
| 11. PDMS, PDS, Designer |
| 12. civil engineer |
| 13. STEEL STRUCTURAL DESIGNER |
| 14. Senior Naval Architect/ Structural Engineer |
| 15. PDS/PDMS Structural Designer |
| 16. Experienced Structural Engineer and more than four years as Strucad Designer |
| 17. X-STEEL DESIGNER |
| 18. Structural Designer PDMS |
| 19. Principle Piping Designer, Piping Design Lead, Bentley Rebis |
| 20. Structural Aerospace Engineer |
| |
| |
| Other CVs; view more oil and gas CVs |
| 1. TEKLA STRUCTURES XSTEEL CIVIL STRUCTURAL DESIGN |
| 2. Master, Unlimited Tonnage, Oceans, Unlimited Radar, GMDSS, STCW95 USCG 2/2012 |
| 3. Technician - installation, verification, regulation, demarrage |
| 4. QA/QC, Welding Inspector |
| 5. Piping Mechanical Engineering |
| 6. Logistics, Warehousing, supply chain, Dispatcher |
| 7. IT Networking, IT administration, Electronic technichian |
| 8. CODED WELDER |
| 9. Welding Engineer, AASHTO, ASME, ASTM, and AWS |
| 10. HVAC Engineer KEPPELFELS OFFSHORE & MARINE LIMITED |
| 11. Experienced electrician |
| 12. Instrument and Controls Technician works in oil and gas fields |
| 13. Instrument Technician Brunel Energy Doha Qatar |
| 14. Experienced scaffolder, NVQ Level 3 C.I.T.B, Advanced ticket CSIRS |
| 15. HR Assistant Manager |
| 16. QC Inspector, Heavy engineering, Oil and Gas field (EPC), Petrofac Engg & Cons Sharjah UAE |
| 17. Document Controller Green Diesel Project, Al Jaber Energy Services in Abu Dhabi |
| 18. Piping designer PDMS user Citec Engineering India Pvt. Ltd., Navi Mumbai Larsen and Toubro Ltd |
| 19. Vessel Master / Skipper GMDSS GOC Southern Moves Fishing, QLD, Western Tuna, Western Australia |
| 20. Rig Electrician on DP2 Deep Drill Ship in West Africa Offshore Ghana FPSO/Bow loading system |
| 21. Structural designer software knowledge in Micro Station, Pro-e, MDT, Solidworks, Solid Edge |
| 22. Trainee electrical graduate, no relevant work experience |
| 23. IT Manager / CAD Support Manager WS Atkins & Partners Overseas Dubai UAE, and India |
| 24. Project Cost Controls Manager Oil & Gas detail engineering procurement construction offshore onshore |
| 25. TRAINEE INDIAN WORKER HAVE KNOWLEDGE OF COMPUTER OPERATIONS |
| 26. NDT Supervisor Neste Oil Maasvlakte Netherlands SLOE powerplant Vlissingen Kuwait Petroleum Shell |
| 27. Civil Site Engineer experienced in Construction Oil and Gas Field Gulf Countries UAE ADCO Abu Dhabi |
| 28. Process Engineer experienced in operating & monitoring Oleflex Plant MTBE Malaysia Sdn Bhd Petronas |
| 29. Oilfield Radio Operator Inmarsat-A, Inmarsat-B, Inmarsat-C, Inmarsat-F, V-Sat, SSB, VHF & Aero VHF |
| 30. Civil/Structure Supervisor Chiyoda Singapore EPCM Contractor Air Liquide Engineering Bechtel |
| |
| |
|
|
|